Brief

Cotswold Transport Planning were appointed to prepare a CTMP to aid our client with discharging a Condition on their Residential Consent, so that work could commence on site.

 

 

Issues & Solutions

A critical issue of the CTMP was the conflict between deliveries associated with the construction by large HGVs and local residents traffic.

In order to strike a balance between an efficient build programme whilst minimising disruption to local residents measures were put in place to ensure that deliveries would avoid peak hours. This ensured a minimal impact on peak congestion and disruption to residents and a nearby college.

Results

The CTMP enabled construction to be carried out as per the Planning Consent.